Smart Brickell

25 Story Smart Brickell Going Vertical

Smart Brickell Construction

Smart Brickell Construction

Construction has started to go vertical on the three tower Smart Brickell, which will have 170 residential units, 150 hotel rooms and 30,000 square feet of retail space.

The 1.23 acre site was purchased for $21.6 million in June 2017 by Habitat Development. Demolition on the site started in November 2018 with a groundbreaking in 2019.

Smart Brickell will be completed in 2021.

Demolition Begins At Smart Brickell Site

Smart Brickell Rendering

Smart Brickell Rendering

Demolition has started on the three tower Smart Brickell Tower in West Brickell located at 229 SW 9th Street.

Currently being demolished are low rise apartment buildings and a house that were built between 1925 and 1972.

Habitat Group purchased the 1.23 acre site in June 2017 for $21.6 million.

Smart Brickell will have 170 condos, 150 hotel rooms and 30,000 square feet of retail space, including a spa, sky bar and café.

Groundbreaking is expected early 2019 with completion in 2020.

Habitat Development Purchase $21.6M Site In West Brickell

Smart Brickell Site in West Brickell

Smart Brickell Site in West Brickell

Habitat Development has purchased  a 1.23 acre site in West Brickell for $21.6 million located between SW 2nd Ave and SW 3rd Ave along SW 9th St, according to The Real Deal.

Habitat Development plan to build three towers called Smart Brickell that will each have 50 hotel rooms, two towers will have 50 residential units and one tower will have 70 residential units.

Construction is expected to start second quarter 2018 and be completed by early 2020.

Smart Brickell is another project that is transforming West Brickell over the past 3-5 years.